The scheme spread over an area of 4350 kanals is adjusted to Gulberg Green (IBECHS) and located on Japan Road Zone-V of Islamabad Capital Territory at a distance of 24 Km from Zero point, Islamabad. Planning & designing of the scheme was carried out by NESPAK. The scheme is approved by CDA.
Project Details
| Location | Japan Road, Zone-V, Islamabad |
| Size of Scheme / Area | 4350 Kanals |
| Development Works | 99% (Substantially Completed) |
Plots Alloted / Vacant
Residential
| CREATED | ALLOTTED | VACANT |
|---|---|---|
| 2344 | 2010 | 334 |
Commercial
| CREATED | ALLOTTED | VACANT |
|---|---|---|
| 216 | 16 | 200 To be Auctioned |
Country Homes Phase-1
| CREATED | ALLOTTED | VACANT |
|---|---|---|
| 50 | 44 | 06 |
Apartments
| CREATED | ALLOTTED | VACANT |
|---|---|---|
| 120 | 39 | 81 First Come First Serve |
Present Status
DEVELOPMENT WORKS BY FWO:
99% progress has been achieved and balance works will be completed shortly.
WATER SOURCE DEVELOPMENT:
Four overhead & four underground water reservoirs have been completed.
Tube well installed within the housing scheme for interim supply of water.
ELECTRIFICATION BY IESCO:
Underground Electrification Work is in progress. Interim supply has been made available and further work on independent feeder line is in progress inside the scheme. The work of feeder line along Japan Road is held up due to intervention of miscreants.
APPROACH ROAD THROUGH IBECHS:
The Board approved the proposal to have access to the scheme through Gulberg Greens, a project of IBECHS. In this regard an agreement was signed on 03.09.2015. Further process is underway.
Future Plans
- Handing over Possession of plots
- Construction of Apartment Blocks
- Construction of Sewage Treatment Plant
- Internal Electrification / Street lights Works
- External Water Supply Infrastructure
- Construction of School, Mosque & Parks etc.
Revised Layout Plan For OPF Housing Scheme, Zone-Islamabad
Layout Plan For OPF Housing Scheme, Zone-V, Islamabad